A) path with the least variance.
B) path with zero slack.
C) path with the most activities.
D) path with the largest variance.
E) None of the above
Correct Answer
verified
Multiple Choice
A) time
B) cost
C) resource requirements
D) predecessors
E) All of the above
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) 21 days.
B) 14 days.
C) 23 days.
D) 32 days.
E) None of the above
Correct Answer
verified
Multiple Choice
A) B
B) D
C) E
D) C
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
E) None of the above
Correct Answer
verified
Multiple Choice
A) 10
B) 12
C) 9
D) 11
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 0
B) 5
C) 3
D) 6
E) None of the above
Correct Answer
verified
Multiple Choice
A) employee scheduling plan.
B) PERT/CPM network diagram.
C) critical path.
D) work breakdown structure.
E) variance calculations for each activity.
Correct Answer
verified
Multiple Choice
A) 4
B) 10
C) 14
D) 25
E) None of the above
Correct Answer
verified
Multiple Choice
A) probabilistic evaluation and review technique.
B) program evaluation and review technique.
C) probability of expected run times.
D) program of expected run times.
E) project evaluation and review technique.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) 4
B) 10
C) 14
D) 25
E) None of the above
Correct Answer
verified
Multiple Choice
A) 108.0
B) 160.4
C) 166.5
D) 135.0
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 81 - 100 of 134