A) milestones.
B) S-curves that plot expenditures against time.
C) S-curves that plot planned expenditures against time.
D) a tracking Gantt chart.
Correct Answer
verified
Multiple Choice
A) the difference between the earned value and the actual cost.
B) the difference between the earned value and the planned value.
C) the difference between the actual cost and the planned value.
D) the difference between the cost and schedule performance indices multiplied by the budgeted cost at completion.
Correct Answer
verified
Multiple Choice
A) 1.24
B) 0.93
C) 0.81
D) 0.76
Correct Answer
verified
Multiple Choice
A) only positive deviations from the schedule baseline with a tracking Gantt chart.
B) only negative deviations from the schedule baseline with a tracking Gantt chart.
C) both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
D) both positive and negative deviations from the budget with the tracking Gantt chart.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) $7,800
B) $9,600
C) $8,400
D) $6,900
Correct Answer
verified
Multiple Choice
A) main phase.
B) formation phase.
C) close-out phase.
D) build-up phase.
Correct Answer
verified
Multiple Choice
A) a single project manager with a single metric system.
B) aggregation of all earned value measures across the firm's entire project portfolio.
C) only positive variances for both budget and schedule.
D) only negative variances for both budget and schedule.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12.
B) The project never experiences negative variance.
C) The project is further behind budget from weeks 0 through 16 than from 24 through 40.
D) The project is in a constant state of positive variance.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) labor hours versus money expended.
B) money expended versus elapsed time.
C) elapsed time versus labor hours.
D) number of personnel versus days behind schedule.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the project baseline.
B) the reporting relationships among members of the project team.
C) what to measure.
D) trigger points.
Correct Answer
verified
Multiple Choice
A) $9,600
B) $7,800
C) $8,100
D) $10,500
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) performance and cost.
B) cost and schedule.
C) time.
D) performance.
Correct Answer
verified