The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.

A) True
B) False

Correct Answer

verifed

verified

Without a __________ budget a good project schedule and cost control are impossible.

Correct Answer

verifed

verified

time-phased
Explanation: A budget alone ...

View Answer

Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.

A) True
B) False

Correct Answer

verifed

verified

Why is a schedule not a schedule until resources have been assigned? Provide a real life example that illustrates your explanation.

Correct Answer

verifed

verified

Resource leveling or smoothing is only used on projects which are resource constrained.

A) True
B) False

Correct Answer

verifed

verified

False

In a resource-constrained project the third priority in assigning resources is usually given to activities with the


A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

If resources are truly limited and activity time estimates are accurate,the resource-constrained schedule will materialize as the project is implemented,not the time-constrained schedule.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?


A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

Resource dependency takes priority over technological dependency but it does not violate it.

A) True
B) False

Correct Answer

verifed

verified

Splitting an activity can result in all of the following EXCEPT


A) More people working on the same activity.
B) Possible startup and shutdown costs.
C) A resource being moved from one activity to another and then back.
D) Activity work being placed on hold for a period until more resources are available.
E) A better project schedule.

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

A

Too many parallel activities for one individual is an example of a resource constraint.

A) True
B) False

Correct Answer

verifed

verified

Sam,the project engineer,has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of what type of resource constraint?


A) Physical
B) Technical
C) People
D) Equipment
E) Time

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

When scheduling activities in a resource-constrained project,typically the activity scheduled first has the __________ amount of slack.

Correct Answer

verifed

verified

least
Explanation: In resource-constrain...

View Answer

Startup and shutdown costs are major considerations when using the ________________ scheduling technique.

Correct Answer

verifed

verified

splitting or multitasking
Expl...

View Answer

All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.

A) True
B) False

Correct Answer

verifed

verified

All of the following are types of resource constraints EXCEPT


A) Materials.
B) People.
C) Equipment.
D) Information.
E) Human.

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?

Correct Answer

verifed

verified

Answer will vary

In a resource-constrained project the second priority in assigning resources is usually given to activities with the


A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

A(n)________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.

Correct Answer

verifed

verified

technical or logic
Explanation: The star...

View Answer

When classifying projects,________ constrained means that a specific resource is fixed and the duration of the project is flexible.

Correct Answer

verifed

verified

resource
Explanation: In sched...