A project manager learns that her project has an EV of 1200, AC of 1100 and PV of 1000.What can the project manager report regarding this project?

Correct Answer

verifed

verified

The project has a position CV of $100.Th...

View Answer

The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the


A) PCIC.
B) VAC.
C) CPI.
D) SPI.
E) TCPI.

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

In calculating schedule variance and cost variance, a negative variance indicates a desirable condition, and a positive variance suggests problems.

A) True
B) False

Correct Answer

verifed

verified

The earned value system starts with the time-phased costs that provide the project baseline, which is called the


A) Planned budgeted value of work scheduled.
B) Planned budgeted value of work completed.
C) Earned value of work scheduled.
D) Scheduled value of work scheduled.
E) Scheduled value of work completed.

F) C) and D)
G) C) and E)

Correct Answer

verifed

verified

Earned value is defined as the budgeted cost of the actual work performed.

A) True
B) False

Correct Answer

verifed

verified

A project manager notices that $1,000 worth of work that was scheduled to be completed at this time has not been accomplished.They know this by looking at the


A) EV.
B) TCPI.
C) SV.
D) PCIB.
E) EAC.

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

The baseline is derived from merging information from the work packages with the project network.

A) True
B) False

Correct Answer

verifed

verified

Given that the AC = 300, PV = 400 and EV = 500, this project is _________ budget.

Correct Answer

verifed

verified

under
Explanation: The cost va...

View Answer

________ holds people accountable, prevents small problems from mushrooming into large problems, and keeps focus.

Correct Answer

verifed

verified

Control
Explanation: Control holds peopl...

View Answer

Identify and describe two methods for tracking and trending schedule performance.

Correct Answer

verifed

verified

The only accurate method for determining...

View Answer

The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.

Correct Answer

verifed

verified

planned value
Explan...

View Answer

Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333.How is the project doing in terms of schedule?


A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost less than planned
E) There is not enough information to draw a conclusion

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

A Cost/Schedule graph can be interpreted using ___________ and __________ for its axis.


A) Earned Value; Schedule
B) Dates; Actual Cost
C) Baseline; Deadline
D) Dollar Amounts; Schedule

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Which of the following is NOT true regarding scope creep?


A) It commonly occurs late in projects.
B) It is frequently unnoticed until time delays or cost overruns are observed.
C) It wears down team motivation and cohesiveness.
D) Project suppliers resent frequent changes.
E) Scope changes can represent significant opportunity.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

A Control Chart can be used to estimate schedule trends.

A) True
B) False

Correct Answer

verifed

verified

The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.

A) True
B) False

Correct Answer

verifed

verified

The final step in the project control process for measuring and evaluating project performance is to take appropriate ________.

Correct Answer

verifed

verified

action
Explanation: The final step in th...

View Answer

The earned value of a project is the


A) Project cost to date adjusted for project scope changes.
B) Total project cost to date.
C) Cost incurred minus the planned cost.
D) Percent of the original budget that has been earned by actual work.
E) The planned time-phased baseline of the value of work scheduled.

F) All of the above
G) C) and D)

Correct Answer

verifed

verified

The best method for assigning costs to the baseline under the 50/50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.

A) True
B) False

Correct Answer

verifed

verified

Rachel notices that the current EV for her project is higher than both the PV and the AC.Rachel has reason to be concerned.

A) True
B) False

Correct Answer

verifed

verified